Introduction to the Project
The Federal Capital Territory Administration has flagged off the construction of a 198-kilometre water distribution network in Bwari, a project designed to provide potable water to nearly 500,000 residents of the satellite town. The project, awarded to CGC Nigeria Limited, was originally slated for completion within 18 months, but the contractors have been tasked to deliver before the third year anniversary of President Bola Ahmed Tinubu’s administration.
Project Objective and Scope
Performing the flag-off on Wednesday, the Minister Nyesom Wike, said the project was a practical demonstration of President Tinubu’s commitment to extend development beyond the city centre to the satellite towns. “One thing you must give to the President is that when he makes his promises, he always fulfills his promises. Today, we are in Bwari. Tomorrow, we will be in Karu. By the next budget, we will be able to go to Kuje and Kwali. And then by 2027, we’ll have taken over Gwagwalada and Abaji. So by the time Mr. President’s four-year tenure expires, all the satellite towns would have been touched by providing them clean, potable water,” he said.
Project Timeline and Funding
To fast-track delivery, Wike explained that the President has already approved and released 50 percent of the total contract sum. “The contract for this ought to be 18 months, but we discussed with the contractors and pleaded with them that they have to do all it takes so that by the third year anniversary of Mr. President, we’ll be able to commission these projects. And when the contractors assured us they will try as much as they could, Mr. President immediately approved the release of 50 percent of the total contract sum to CGC Nigeria Limited.”
Community Involvement and Project Protection
He therefore urged residents to safeguard the project, describing it as one of the most important investments ever made in their community. “This will stop you from digging your own boreholes, providing tanks and the rest. All you need to do is to just link up to the general water source, and then the water will flow; clean water, treated water, unlike the one we do in our boreholes, not treated. This is fully treated water.” He appealed to traditional rulers, women and youth to take ownership of the project and protect it against vandalism.
Project Benefits and Expected Outcomes
In her remarks, FCT Minister of State, Dr. Mariya Mahmoud affirmed that access to clean and potable water, would enhanced public health and the quality of life in Bwari in particular and FCT in general. While expressing gratitude to President Bola Ahmed Tinubu, for his visionary leadership, and for placing critical infrastructure such as water supply at the heart of his Renewed Hope Agenda, Mahmoud, applauded the FCT Administration under the leadership of Barrister Nyesom Wike for his dedication and diligence in service delivery.
Project Details and Technical Overview
Giving an overview of the project, the Acting Executive Secretary of the Federal Capital Development Authority, Engr. Richard Dauda, said the project was a strategic infrastructure initiative aligned with the FCT Regional Master Plan, designed to deliver secondary and tertiary water distribution networks to underserved communities. He explained that the scope of works includes site clearance, excavation, and the installation of about 198 kilometres of pipes ranging from 60 millimetres to 600 millimetres in diameter, with fittings, joints, flanges and valve chambers.
Conclusion
The construction of the 198-kilometre water distribution network in Bwari is a significant project that will provide potable water to nearly 500,000 residents of the satellite town. The project is expected to be completed before the third year anniversary of President Bola Ahmed Tinubu’s administration and will have a positive impact on the public health and quality of life in Bwari and the FCT in general.
FAQs
Q: What is the purpose of the 198-kilometre water distribution network in Bwari?
A: The purpose of the project is to provide potable water to nearly 500,000 residents of the satellite town.
Q: Who is the contractor awarded the project?
A: The project was awarded to CGC Nigeria Limited.
Q: What is the expected completion time of the project?
A: The project is expected to be completed before the third year anniversary of President Bola Ahmed Tinubu’s administration.
Q: How will the project benefit the community?
A: The project will provide clean and potable water, enhance public health, and improve the quality of life in Bwari and the FCT in general.
Q: What is the scope of works for the project?
A: The scope of works includes site clearance, excavation, and the installation of about 198 kilometres of pipes ranging from 60 millimetres to 600 millimetres in diameter, with fittings, joints, flanges and valve chambers.